Dynamics 365 test automation: why do customisations break at a release wave?
Microsoft updates Dynamics 365 twice a year, in April and October, and the update reaches production too. Standard features rarely break; your own customisations — JavaScript, plug-ins, legacy form controls, deprecated APIs, PCF components, Power Automate flows and integrations — do. The answer is a risk-based automated regression suite of 30–50 test cases that runs against the early access version of the wave in a sandbox, weeks before production is updated.
What is a release wave, and when does it arrive?
A release wave is Microsoft’s half-yearly update to Dynamics 365 and the Power Platform. Wave 1 starts rolling out in April, wave 2 in October, reaching every tenant in stages over the following months. Microsoft publishes the content in advance in the release plans and announces removals in its list of deprecations.
Roughly two months before general availability, the wave can be switched on in a sandbox through early access. Those six to eight weeks are when a defect can still be found and fixed in the test environment. Skip them, and you learn what broke on the morning of the production update — from your users.
Why do customisations break, and not standard features?
Microsoft tests standard features itself before every wave. Nobody at Microsoft knows your own developments: the JavaScript waiting for a form field to load, the plug-in relying on a particular message order, the Power Automate flow watching a field’s old value. The wave changes their environment, and that is what breaks them — often without an error message.
| Component | What is at risk | What we test |
|---|---|---|
| Custom JavaScript on forms | unsupported DOM access, deprecated Xrm.Page calls, timing-dependent code; silently stops when the UI changes | hidden fields, default values, required fields, buttons on the form |
| Plug-ins and custom workflow activities | changed message order or platform behaviour, deprecated SDK calls, timeouts | the result of business logic that runs on save or status change |
| Legacy form controls and old UI elements | Microsoft retires them; the feature disappears or behaves differently | appearance and behaviour of the affected forms |
| Deprecated APIs | an announced removal takes effect in a later wave | integrations, scripts and reports that call the old endpoint |
| PCF components | a version change in the framework or its libraries | loading, data handling and saving of the custom control |
| Power Automate flows | connector or trigger changes, changed field values | approvals, notifications, document generation end to end |
| Integrations (ERP, invoicing, web shop) | a change on the CRM side causes an error in the other system | data exchange field by field, also below the UI (API tests) |
| Standard features | rarely break; Microsoft tests them itself | only as part of our own processes, not separately |
The common thread: the more customisations and integrations, the higher the risk, and the more expensive it is to click through the system by hand before every wave. That is why the release wave is the strongest argument for test automation on Dynamics 365.
What does a release wave regression process look like?
- 1Risk-based test suite
We do not automate everything. Business-critical and customised processes are ranked — lead → quote → order, case → SLA → resolution, ERP hand-over — and the first 30–50 test cases come from that. On a medium system that covers roughly 80 % of the risk.
- 2Nightly runs in CI
The suite runs every night and before every deployment (Azure DevOps, GitHub Actions, Jenkins). Before the wave we already know everything is green on the current version — so anything red later is red because of the update.
- 3Early access in the sandbox
We enable the wave’s early access in a sandbox refreshed from production and run the full regression suite there.
- 4Analysing failures
For every red test we decide: a real defect in the system, or only a UI change (new layout, renamed button)? Based on screenshots, logs and the Plugin Trace Log.
- 5Fix the system or the test
For a real defect we fix the customisation (for example by replacing unsupported JavaScript); for a UI change we adjust the test. Then we re-run until everything is green.
- 6Release decision
A test summary: what ran, what failed, what is still open. On that basis we let the update into production.
Which tool: Tricentis Tosca, Katalon or Playwright?
Detailed comparison: Tricentis Tosca, Katalon or Playwright? With any of the three, we also check integrations below the UI with API tests (Postman, Newman in CI).
What do we test by hand, and what automatically?
Automation protects what exists; it does not test what is new. The wave’s new features and changed UI are reviewed by hand, because they need human judgement: is the new feature needed, will it confuse users, should it be switched on?
Where the line lies and when automation pays off is shown in a worked example: manual vs automated testing — when does it pay off?
How do we do this within a support retainer?
Under a monthly Dynamics 365 support retainer, release wave preparation is part of the service, not a separate project:
Service details and tools: software testing and test automation.
Why does it matter that CRM consultants and test engineers are one team?
At a release wave, a failed test is only half the question. The other half: why did it fail, and what needs fixing — the JavaScript, the plug-in, the flow or the test? When the tester and the Dynamics consultant sit in two different companies, that question bounces between tickets for weeks. With us, the same team builds the customisation, writes the test and analyses the failure; the Dynamics CRM exams (MB2-704, MB2-707, MB5-705) and the Tricentis Tosca certifications sit in the same team.
Frequently asked questions
When is the Dynamics 365 release wave?
Twice a year: wave 1 starts rolling out in April, wave 2 in October, reaching every tenant in stages over the following months. With early access it can be tried in a sandbox roughly two months earlier.
Can a release wave be postponed?
Not indefinitely. The update is mandatory and reaches production at the tenant’s scheduled update time. That is why the tests must run in the sandbox during early access.
How many test cases should be automated?
On a medium system, 30–50 risk-based test cases cover roughly 80 % of the risk. The goal is not a count but coverage of business-critical and customised processes.
How quickly is a regression suite running?
The first round covers the most critical processes with automated tests, already running in CI; from then on the suite keeps growing.
Do we need a separate test environment?
Yes, we never run tests in production. You need a sandbox refreshed from production in which the wave’s early access can be enabled.